Anantapur Project
Project Capacity
This is a 100MW Solar Power Plant.
REC/Non-REC
This project is using REC route and signing PPAs with Open Access Consumers.
Land
NNR has acquired around 600 acres of land in Anantapur district, AP. Out of this 600 acres around 500 acres of land is already converted into non-agriculture land which is a prerequisite to use for commercial purposes.
Location

View Larger Map
 
Permissions
a). Grid Connectivity: We applied for avacuation permission to AP TRANSCO on March 7th, 2013 and got approval on August 28th 2013.

b). Single Window Approvals: Already applied for necessary permissions from the following departments/boards and expecting approvals at any time.
  • Gram Panchayat
  • Factories Department
  • Power Feasibility
  • AP Pollution Control Board
  • Ground Water Department
  • Fire Department
    PPA (Power Purchase Agreement)
    NNR has been talking to several Open Access big consumers. We are expecting to sign PPAs by the end of August 2013. We are also exploring the possibility of bringing in equity for this project from these open access consumers to utilize waiver of cross subsidy surcharge.
    Financial Closure & EPC
    NNR has been talking to several EPC contractors and Equipment Suppliers. We have been working on several models to develop this project without waiting to raise debt from financial institutions.

    Most likely this process may be completed by the end of September 2013 and work may be started on this project in October 2013.
    Technology

    We are evaluating both thin film and crystalline technologies. Selection of the technology depends on several factors including the supplier and EPC contractor.

    Commissioning Date

    Expected date for full commissioning of this project is 31st March 2014.    This will be done in phases.

    NNR's Documents
    Solar Power MOU
    Commercial Land Bank
    Transco-Mahabubnagar Perm..
    Transco-Anantapur Perm..
    IEM
    Transco-Anantapur-SS-Cha..
    App - Power Supply To AP
    Annual Accounts - 2012-13
    Annual Accounts - 2013-14-1
    Mahabubnagar Land Bank
       
    NNR's Presentations
    Prestige
    Tata
     
    Public Documents
    The Electricity Act, 2003
    The Electricity Rules, 2005
    Open Access In ISTR, 2008
    AP Solar Power Policy, 2012
    AP Tariff Schedule, 2013-14
    AP Cross Subsidy, 12-13
    BS, Power Prices, 03-07-13
       
     
     
    Home | About Us | Projects | Suppliers / Contractors | Customers | Investors | Contacts | Useful Links | FAQs
    Copyright © 2013 NNR Group.