| Anantapur Project |
|
|
|
|
| This is a 100MW Solar Power Plant. |
|
|
| This project is using REC route and signing PPAs with Open Access Consumers. |
|
|
NNR has acquired around 600 acres of land in Anantapur district, AP. Out of this 600 acres around 500 acres of land is already converted into non-agriculture land which is a prerequisite to use for commercial purposes.
|
|
|
View Larger Map |
| |
|
|
Permissions |
|
a). Grid Connectivity: We applied for avacuation permission to AP TRANSCO on March 7 th, 2013 and got approval on August 28 th 2013.
b). Single Window Approvals: Already applied for necessary permissions from the following departments/boards and expecting approvals at any time.
Gram Panchayat
Factories Department
Power Feasibility
AP Pollution Control Board
Ground Water Department
Fire Department
|
|
|
PPA (Power Purchase Agreement) |
|
NNR has been talking to several Open Access big consumers. We are expecting to sign PPAs by the end of August 2013. We are also exploring the possibility of bringing in equity for this project from these open access consumers to utilize waiver of cross subsidy surcharge. |
|
|
NNR has been talking to several EPC contractors and Equipment Suppliers. We have been working on several models to develop this project without waiting to raise debt from financial institutions.
Most likely this process may be completed by the end of September 2013 and work may be started on this project in October 2013.
|
|
|
We are evaluating both thin film and crystalline technologies. Selection of the technology depends on several factors including the supplier and EPC contractor. |
|
|
Expected date for full commissioning of this project is 31st March 2014. This will be done in phases. |
 |
| |