| This is a 200MW Solar Power Plant. |
|
|
| This project is using REC route and signing PPAs with Open Access Consumers. |
|
|
NNR is in the process of acquiring around 800 acres of land in Mahabubnagar district, AP. By the end of July 2013 entire land registration is expected to be completed. |
|
|
View Larger Map |
| |
|
|
Permissions |
|
a). Grid Connectivity: We applied for avacuation permission to AP TRANSCO on March 7 th, 2013 and got approval in July 2013.
b). Single Window Approvals: We are in the process of applying for necessary permissions from the following departments/boards.
Gram Panchayat
Factories Department
Power Feasibility
AP Pollution Control Board
Ground Water Department
Fire Department
|
|
|
PPA (Power Purchase Agreement) |
|
NNR has been talking to several Open Access big consumers. We are expecting to sign PPAs by the end of October 2013. We are also exploring the possibility of bringing in equity for this project from these open access consumers to avail waiver of expensive cross subsidy surcharge. |
|
|
NNR has been talking to several EPC contractors and Equipment Suppliers. We have been working on several models to develop this project without waiting to raise debt from financial institutions.
Most likely this process may be completed by the end of November 2013 and work may be started on this project in January, 2014.
|
|
|
We are evaluating both thin film and crystalline technologies. Selection of the technology depends on several factors including supplier and EPC contractor. |
|
|
Expected date for full commissioning of this project is 30th June, 2014. This will be done in phases. |
 |
| |